Cisco IP Telephony: Planning, Design, Implementation, Operation, and Optimization [Electronic resources] نسخه متنی

اینجــــا یک کتابخانه دیجیتالی است

با بیش از 100000 منبع الکترونیکی رایگان به زبان فارسی ، عربی و انگلیسی

Cisco IP Telephony: Planning, Design, Implementation, Operation, and Optimization [Electronic resources] - نسخه متنی

Ramesh Kaza; Salman Asadullah

| نمايش فراداده ، افزودن یک نقد و بررسی
افزودن به کتابخانه شخصی
ارسال به دوستان
جستجو در متن کتاب
بیشتر
تنظیمات قلم

فونت

اندازه قلم

+ - پیش فرض

حالت نمایش

روز نیمروز شب
جستجو در لغت نامه
بیشتر
لیست موضوعات
توضیحات
افزودن یادداشت جدید







Preimplementation Tasks


This section contains checks to ensure that the following high-level preimplementation tasks are completed before you start deploying the IPT solution:

Project plan

Site information

Implementation team



Project Plan


The project manager who is assigned to the deployment project develops the project plan for implementing the IPT solution. You should contact the project manager to obtain the project plan and ensure that, at minimum, the high-level tasks listed in Table H-1 are included in the project plan.

Table H-1. Project Plan Tasks Verification

No.

Task Category

Included in the Project Plan?

1

Preimplementation preparations: procure all required equipment, establish the right contacts, and so on.

Yes

No

2

Site survey tasks: check the readiness of the site

Yes

No

3

IPT implementation procedure: actual implementation of IPT components

Yes

No

4

IPT add-on feature implementation: complete the implementation of additional applications such as AutoAttendant, Unity, and features in CallManager such as extension mobility and IP Manager Assistant (IPMA)

Yes

No

5

Acceptance tests: test-case scenarios that need to be successfully executed on the deployed solution

Yes

No

6

Post-implementation documentation: document the network topology and configurations

Yes

No

7

Customer acceptance: sign-off process in which the customer acknowledges project completion

Yes

No


Site Information


Collecting the site information ahead of time helps you to obtain the necessary permissions for the implementation staff to enter the buildings within the sites beforehand (see Table H-2). In addition, if the deployment involves multiple sites, the project manager can plan for the additional remote resources required to perform the implementation at these sites.

Table H-2. Site Information

No.

Question

Answer

1

What is the company name?

Company name:

2

What is the site address?

Street:

City:

State:

Country:

Zip code:

Phone:

Fax:

3

Is building access approval required?

Yes

No

4

Does everyone in the deployment team have access to the building and the server rooms?

Yes

No

5

What are the normal hours of operation in the building?

Working hours:

6

Are any special access permissions required to work after hours?

Yes

No

7

Who is the site coordinator contact?

Name:

Work phone:

Cell phone:

E-mail:

Pager:

8

Which room is designated for the equipment staging?

Room location:

9

Does the project team have an office space in which to work, equipped with office supplies, printers, and network connectivity at all the site locations?

Yes

No


Implementation Team


An implementation team is the key to the successful deployment of the IPT network.

/ 151